Yapı Kredi GES
| Province | Project Name | kWe | kWp |
|---|---|---|---|
| Tekirdağ | Yapı Kredi GES | 25.000,0 | 33.000,0 |
End-to-End Business Development
Regional Analysis, Constraint Assessment and Site Identification: Within the scope of the project we carried out on behalf of Yapı ve Kredi Bankası A.Ş, we completed geological, technical, ownership and grid constraint analyses in full in the light of our digital data bank and identified the most feasible project site.
Grid Modelling and the Right Connection Point: By modelling the grid infrastructure from multiple angles, we determined the right grid connection point for the safest transmission of energy; we developed optimised engineering designs that reduce investment and operating costs.
Scenario Development, 3D Modelling and Simulation: We created multiple scenarios for our investor’s corporate consumption and capacity requirements and investment targets; we prepared different layout alternatives according to the site’s topographic and meteorological dynamics, advanced 3D shading models and generation simulations.
Technical and Financial Feasibility and the BAÇM Application: In line with the comprehensive technical and financial feasibility studies we prepared, we completed the applications for the Call Letter for the Connection Agreement (BAÇM).
Capacity Allocation and Multi-Agency Permit Management: After obtaining the call letter and capacity allocation, we obtained all required official opinions from nearly forty authorised public institutions and organisations (DSİ, General Directorate of Forestry, Cultural Heritage, Highways, TEİAŞ, TEDAŞ, etc.) in the business development, ÇED and zoning planning processes.
Social Consensus and Local Stakeholder Management: At the same time, we fully achieved social consensus on site by building a transparent, trust-based and sustainable bridge of communication with the local community and local administrations.
ÇED Decisions, Non-Agricultural Use Permits and Finalisation of Zoning: In line with these institutional opinions, whose currency and suitability were continuously monitored at every step up to the permit stage, we concluded the ÇED decisions and non-agricultural use permits. We finalised the master and implementation zoning plans, based on existing-condition mapping and ground surveys, by completing the statutory public display periods.
Optimum Line Surveys and Engineering Project Approvals: We carried out energy distribution and transmission line (ENH/EİH) route surveys that minimise transmission losses, optimise the investment budget and provide the highest grid security; we obtained approval for detailed electrical, structural and infrastructure engineering projects compliant with TEDAŞ and TEİAŞ standards.
Execution of the Agreement and Handover of the Permitted Site: With the execution of the connection agreement and the final construction permit obtained, we handed over the project site to our investor complete and ready for the turnkey EPC (installation) phase.