| Province | Project Name | kWe |
|---|---|---|
| Malatya | GES | 12.500,0 |
End-to-End Business Development
Site Identification and Constraint Analysis: Geological, technical, ownership and grid constraint analyses were carried out based on regional strategic studies and our digital data infrastructure, and the most feasible project site was identified.
Grid Modelling and Connection Point Identification: The right grid connection point to ensure safe and uninterrupted transmission of energy was identified, and optimised engineering designs that reduce investment and operating costs were developed.
Scenario Development and Simulation: Multiple scenarios in line with consumption and capacity targets were developed; different layout alternatives based on topographic data, 3D shading analyses and generation simulations were modelled.
Official Application and Call Letter (BAÇM): Official applications were completed in line with the technical and financial feasibility reports, the Call Letter for the Connection Agreement was obtained and capacity allocation was secured.
Institutional Opinions and Social Consensus: During the ÇED and zoning stages, official opinions were obtained from nearly forty public institutions and organisations (DSİ, General Directorate of Forestry, Cultural Heritage, Highways, TEİAŞ, TEDAŞ, etc.); social consensus on site was achieved through sustainable communication with the local community and local administrations.
Finalisation of Environmental and Zoning Plans: In line with institutional opinions whose validity was monitored up to the permit stage, ÇED decisions and non-agricultural use permits were completed; master and implementation zoning plans based on existing-condition maps and ground surveys were finalised following the statutory public display periods.
Transmission Line (ENH/EİH) and Detailed Engineering Approvals: The most optimum route surveys minimising transmission losses were carried out, and electrical, structural and infrastructure implementation projects fully compliant with TEDAŞ and TEİAŞ standards were approved.
Agreement, Final Permit and Completion of Business Development: With the Connection Agreement signed and the final construction permit obtained, all end-to-end business development and permitting processes for the project site were successfully completed; the site was made ready for the turnkey EPC (installation) phase.
ENH and Expropriation: After completing business development and the permit, we took on the construction of the 25 km Energy Transmission Line (ENH) connecting the plant to the grid; we completed all expropriation and ENH construction processes along the line in full and successfully.