Şişecam
| Province | Project Name | kWe | kWp |
|---|---|---|---|
| Kars | Sarıkamış GES-1 | 21.000,0 | 28.283,32 |
| Kars | Sarıkamış GES-1 | 25.000,0 | 32.704,36 |
| Nevşehir | Ürgüp GES-1 | 8.000,0 | 11.576,0 |
| Nevşehir | Ürgüp GES-2 | 12.000,0 | 16.323,0 |
| Gümüşhane | Kelkit GES-1 | 3.000,0 | 3.684,0 |
| Gümüşhane | Kelkit GES-2 | 3.250,0 | 3.854,0 |
End-to-End Business Development
Site Identification and Constraint Analysis: In line with Şişecam A.Ş.’s corporate sustainability targets, geological, technical, ownership and grid constraint analyses were carried out using regional strategic studies and our digital data infrastructure, and the most feasible project site was identified.
Grid Modelling and Connection Point Identification: The right grid connection point to ensure safe and uninterrupted transmission of energy was identified, and engineering designs that reduce both investment (CAPEX) and operating (OPEX) costs were developed.
Scenario Development and Simulation: Multiple scenarios matching Şişecam A.Ş.’s consumption and capacity requirements were developed; layout alternatives based on topographic data, 3D shading analyses and generation simulations were modelled.
Official Application and Call Letter (BAÇM): Official applications were completed in line with the technical and financial feasibility reports, the Call Letter for the Connection Agreement was obtained and capacity allocation was secured.
Institutional Opinions and Social Consensus: During the ÇED and zoning stages, official opinions were obtained from nearly forty public institutions and organisations (DSİ, General Directorate of Forestry, Regional Board for the Conservation of Cultural Heritage, Highways, TEİAŞ, TEDAŞ, etc.); social consensus on site was fully achieved through sustainable communication with the local community and local administrations.
Finalisation of Environmental and Zoning Plans: In line with institutional opinions whose validity was monitored up to the permit stage, ÇED decisions and non-agricultural use permits were completed; master and implementation zoning plans based on existing-condition maps and ground surveys were finalised following the statutory public display periods.
Transmission Line (ENH/EİH) and Detailed Engineering Approvals: The most optimum route surveys minimising transmission losses were carried out, and electrical, structural and infrastructure implementation projects fully compliant with TEDAŞ and TEİAŞ standards were approved.
Handover of the Permitted Site and Completion of EPC: With the Connection Agreement signed and the final construction permit obtained, the project site was handed over ready for the turnkey installation phase; with the EPC construction process subsequently completed, we take rightful pride and joy in the facility being commissioned and starting generation, and in this lasting contribution to Şişecam A.Ş.’s green energy transformation.