Mehmet Dora
| Province | kWe | kWp |
|---|---|---|
| Ankara | 2.000,0 | 2.200,0 |
End-to-End Business Development
Starting with our regional and strategic analysis studies, applications for the Call Letter for the Connection Agreement (BAÇM) were made following site identification and completion of the technical, financial and grid constraint analyses. With the call letter obtained and capacity allocated, the ÇED and zoning planning stages were initiated, and all related institutional procedures were carried out in full throughout the process. Through transparent and sustainable public relations activities carried out simultaneously, social consensus on site was achieved; with the statutory public display periods of the master and implementation zoning plans completed and the plans finalised, the project development phase was successfully concluded.