Koçtaş Yapı ve Marketleri A.Ş.
| Province | Project Name | kWe | kWp |
|---|---|---|---|
| Gümüşhane | Koçtaş GES | 6.500 | 8.034 |
End-to-End Business Development
Site Identification and Constraint Analysis: Within the scope of the project we carried out on behalf of Koçtaş, geological, technical, ownership and grid constraint analyses were carried out based on regional strategic studies and our digital data infrastructure, and the most feasible project site was identified.
Grid Modelling and Connection Point Identification: The right grid connection point to ensure safe and uninterrupted transmission of energy was identified, and engineering designs that reduce investment and operating costs were developed.
Scenario Development and Simulation: Multiple scenarios suited to Koçtaş’s corporate consumption profile and capacity targets were developed; different layout alternatives based on topographic data, 3D shading analyses and generation simulations were modelled.
Official Application and Call Letter (BAÇM): Official applications were completed in line with the technical and financial feasibility reports, the Call Letter for the Connection Agreement (BAÇM) was obtained and capacity allocation was secured.
Institutional Opinions and Sustainable Public Relations: During the ÇED and zoning stages, official opinions were obtained from nearly forty public institutions and organisations (DSİ, General Directorate of Forestry, Cultural Heritage, Highways, TEİAŞ, TEDAŞ, etc.); social consensus on site was fully achieved through transparent and sustainable public relations with the local community, village heads and local administrations.
Finalisation of Environmental and Zoning Plans: In line with institutional opinions whose validity was monitored up to the permit stage, ÇED decisions and non-agricultural use permits were completed; master and implementation zoning plans based on existing-condition maps and ground surveys were finalised following the statutory public display periods.
Transmission Line (ENH/EİH) and Detailed Engineering Approvals: The most optimum route surveys minimising transmission losses were carried out, and electrical, structural and infrastructure implementation projects fully compliant with TEDAŞ and TEİAŞ standards were approved.
Zoning Approvals, Completion and Project Transfer: After all statutory permits and zoning approvals were obtained in full, the completion processes under our contractual commitments were successfully finalised and the project was transferred to Koçtaş.