Koç Okulu (İlk-Orta-Lise)

Province Project Name kWe kWp
Nevşehir Koç Okulu Ürgüp GES 2.100 2.423

End-to-End Business Development

Strategic Site Analysis and Constraint Assessment: Within the scope of the project we carried out on behalf of Koç Schools, we completed geological, ownership and grid constraint analyses with our digital data infrastructure and identified the most efficient site.

Grid Modelling and Optimum Design: We identified the right connection point that guarantees uninterrupted transmission of energy; we developed optimised engineering models that reduce investment and operating costs.

Scenario Development and Simulation: We developed multiple capacity scenarios suited to Koç Schools’ consumption profile and corporate sustainability vision; we prepared 3D shading analyses and generation simulations.

Feasibility and Obtaining the Call Letter (BAÇM): By completing the applications in line with comprehensive technical and financial feasibility reports, we concluded the Call Letter for the Connection Agreement (BAÇM) process and secured capacity allocation.

Institutional Opinions and Sustainable Public Relations: While collecting official opinions from nearly forty authorised public institutions, we achieved social consensus on site through the transparent communication mechanism we established with the local community, village heads and local administrations.

Environmental Permits and Finalisation of Zoning: We concluded the ÇED decisions and non-agricultural use permits; we finalised the master and implementation zoning plans, based on existing-condition maps and ground surveys, following the statutory public display periods.

Transmission Line (ENH/EİH) and Engineering Surveys: Having completed the most optimum line route surveys minimising energy transmission losses, we managed the project approval processes before the relevant institutions.

Permitting Process: In our project, whose zoning planning and approval processes have been successfully completed, the stage of obtaining the final construction permit and preparing the site for the turnkey EPC phase is continuing on the planned schedule.