Hane Otelcilik Turizm Tic ve İnş A.Ş

Province Project Name kWe kWp
Gümüşhane Hane Otelcilik GES 1.630 2.331

End-to-End Business Development

Strategic Site Analysis and Constraint Assessment: We completed technical, ownership and grid constraint analyses and identified the most efficient site.

Grid Modelling and the Right Connection Point: We identified the right connection point to ensure safe and uninterrupted transmission of energy; we developed optimised engineering solutions that reduce investment (CAPEX) and operating (OPEX) costs.

Scenario Development, 3D Modelling and Simulation: We developed multiple scenarios suited to our investor’s corporate electricity consumption profile; we prepared site-specific layout alternatives, 3D shading analyses and generation simulations.

Official Application and Obtaining the BAÇM: By completing the official processes in line with comprehensive technical and financial feasibility reports, we obtained the Call Letter for the Connection Agreement (BAÇM) and secured capacity allocation.

Institutional Opinions and Sustainable Public Relations: While collecting official opinions from nearly forty authorised public institutions during the ÇED and zoning stages, we fully achieved social consensus on site through the transparent and sustainable public relations mechanism we established with the local community, village heads and local administrations.

Environmental Permits and Finalisation of Zoning: In line with institutional opinions whose validity was monitored up to the permit stage, we concluded the ÇED decisions and non-agricultural use permits; we finalised the master and implementation zoning plans following the statutory public display periods.

Transmission Line (ENH/EİH) and Engineering Approvals: We carried out the most optimum route surveys minimising energy transmission losses; we obtained approval for electrical, structural and infrastructure implementation projects to TEDAŞ and TEİAŞ standards.

Execution of the Agreement and Handover of the Permitted Site: By executing the connection agreement and obtaining the final construction permit, we successfully completed the business development and permitting phase of the project site; we handed over the site ready for installation.

EPC Completion, Commissioning and Generation: We take rightful honour and joy in the facility, whose business development and engineering groundwork we completed in full, being commissioned on completion of its EPC installation process and starting clean energy generation.