Demir Export A.Ş.

Province Project Name kWe kWp
Gümüşhane İspir GES 8.850 10.443
Gümüşhane İspir GES-1 8.800 10.004
Gümüşhane İspir GES-2 7.150 10.004

End-to-End Business Development

Strategic Site Analysis and Constraint Assessment: Within the scope of the project we carried out on behalf of Demir Export, we completed geological, technical, ownership and grid constraint analyses in full in the light of our digital data bank and identified the most feasible project site.

Grid Modelling and the Right Connection Point: By modelling the grid infrastructure from multiple angles, we determined the right grid connection point for the safest transmission of energy; we developed optimised engineering designs that reduce investment and operating costs.

Scenario Development, Modelling and Simulation: We created multiple scenarios for Demir Export’s corporate consumption and capacity requirements and investment targets; we prepared different layout alternatives according to the site’s topographic and meteorological dynamics, advanced 3D shading models and generation simulations.

Feasibility and the Call Letter (BAÇM) Application: By completing the official applications in line with comprehensive technical and financial feasibility studies, we obtained the Call Letter for the Connection Agreement (BAÇM) and secured capacity allocation.

Institutional Opinions and Sustainable Public Relations: We obtained all required official opinions from nearly forty authorised public institutions and organisations (DSİ, General Directorate of Forestry, Cultural Heritage, Highways, TEİAŞ, TEDAŞ, etc.) in the business development, ÇED and zoning planning processes; by running transparent, trust-based and sustainable public relations processes with the local community, residents and local administrations, we fully achieved the project’s social consensus on site.

ÇED Decisions, Non-Agricultural Use Permits and Finalisation of Zoning: In line with institutional opinions whose currency and regulatory compliance were continuously monitored at every step up to the permit stage, we concluded the ÇED decisions and non-agricultural use permits; we finalised the master and implementation zoning plans, based on existing-condition mapping and ground surveys, by completing the statutory public display periods.

Optimum Transmission Line (ENH/EİH) and Engineering Approvals: We carried out energy transmission line route surveys that minimise transmission losses, optimise the investment budget and provide the highest grid security; we obtained approval for detailed electrical, structural and infrastructure engineering implementation projects compliant with TEDAŞ and TEİAŞ standards.

Execution of the Agreement and Handover of the Permitted Site: With the execution of the connection agreement and the final construction permit obtained, we handed over the project site to Demir Export complete and ready for the turnkey EPC (installation) phase.

Completion of the Facility, Generation and Commissioning: We take joy and rightful pride in the completion of the installation of the project, whose business development, engineering and permitting groundwork we managed end to end, its start of commercial generation and the value added to Demir Export’s sustainability vision.

ENH Construction and Expropriation: After permitting, we joined forces with our business partner for the facility’s transmission infrastructure; we completed the construction of 25.5 km of overhead and 3.7 km of underground 4x(477) MCM transmission line, together with comprehensive ownership and expropriation services, in a record 150 days and handed it over to our investor.