Bodrum Amerikan Hastaneleri
| Province | Project Name | kWe | kWp |
|---|---|---|---|
| Nevşehir | Bodrum Amerikan Hst. - 1 | 800 | 992 |
| Nevşehir | Bodrum Amerikan Hst. - 2 | 800 | 850 |
| Nevşehir | Bodrum Amerikan Hst. - 3 | 800 | 893 |
End-to-End Business Development
Site Identification and Constraint Analysis: Within the scope of the project we carried out on behalf of the American Hospital, geological, technical, ownership and grid constraint analyses were carried out based on regional strategic studies and our digital data infrastructure, and the most feasible project site was identified.
Grid Modelling and Connection Point Identification: The right grid connection point to ensure safe and uninterrupted transmission of energy was identified, and optimised engineering designs that reduce investment and operating costs were developed.
Scenario Development and Simulation: Multiple scenarios matching corporate consumption and capacity targets for the critical, uninterrupted energy needs of healthcare facilities were developed; different layout alternatives based on topographic data, 3D shading analyses and generation simulations were modelled.
Official Application and Call Letter (BAÇM): Official applications were completed in line with the technical and financial feasibility reports, the Call Letter for the Connection Agreement (BAÇM) was obtained and capacity allocation was secured.
Institutional Opinions and Sustainable Public Relations: During the ÇED and zoning stages, official opinions were obtained from nearly forty authorised public institutions and organisations (DSİ, General Directorate of Forestry, Cultural Heritage, Highways, TEİAŞ, TEDAŞ, etc.); social consensus on site was fully achieved through transparent and sustainable public relations with the local community, village heads and local administrations.
Finalisation of Environmental and Zoning Plans: In line with institutional opinions whose validity was monitored up to the permit stage, ÇED decisions and non-agricultural use permits were completed; master and implementation zoning plans based on existing-condition maps and ground surveys were finalised following the statutory public display periods.
Transmission Line (ENH/EİH) and Detailed Engineering Approvals: The most optimum route surveys minimising transmission losses were carried out, and electrical, structural and infrastructure implementation projects fully compliant with TEDAŞ and TEİAŞ standards were approved.
Agreement and Handover of the Permitted Site: With the Connection Agreement executed and the final construction permit obtained, the business development and permitting phase of the project site was successfully completed; the site was handed over ready for the turnkey EPC (installation) phase.
EPC Completion, Commissioning and Start of Generation: With the subsequent EPC installation process of the project, whose business development and engineering groundwork we delivered in full, also successfully completed, the facility has been commissioned and has started clean energy generation; we take pride in contributing to the green energy transformation of one of our country’s long-established healthcare institutions.